S30V heat treatment

Joined
Sep 29, 2000
Messages
40
I imagine this has been discused before but I just purchased 6' of the stuff and the supplier was suppose to sent the heat treat temps and procedure and never. Does anyone out there have the procedure and temperatures, I think that someone once told me that it needed to be nitrogen quenched, but i hope it is not necessary as I don't have the necessary equipment. Thanks.
Claude
 
Hey there Kelly! Give Thomas a call, as he's been using this stuff the last little while, and I'm sure he's got a great process worked out. He can also hook you up with an outfit in Calgary the does deep cyrogenics for about $5 a blade, with a fairly quick turn around time. If you decide to go with dry ice, MediGas (on Blackfoot Tr.) is the only game in Calgary. Give me a call sometime!

Clint
 
Here's some more info for you:

www.crucibleservice.com/datash/dsS30Vv3.pdf

Recommended Heat Treatment:
Austenitize 1950°F (1065°C). Quench to below 125°F (50°C).
Temper (snap temper) 2 hrs. at 400°F (205°C), deep freeze, and
then double temper at 600°F (315°C) 2 hrs. minimum each temper.
Cool to hand warm between tempers.
Aim hardness: 58-61 HRC.
Tempering Temperature °F (°C)

Steve
 